WestLAND Group was retained by Turner Construction and our involvement in this construction project included reviewing Civil, Architectural and Structure plans and generating RFI’s for any discrepancies found with regards to the building, drainage, and site layout.  WestLAND surveyed the boundary and conducted a design survey on existing improvements in order to review existing with proposed improvements. Data was analyzed and any grading enhancements were field designed as needed.  WestLAND also provided the construction surveying and staking required for the construction of the building, streets, drainage structures, utilities, and parking lots. WestLAND engineers also updated the drainage and grading plans with as-built information which was required by SCE and the city of Alhambra.